Before a carton making machine arrives, check the factory as carefully as the machine specification. A correct working width is only one part of a successful installation. Entry access, floor space, power, material flow and a safe commissioning area determine whether the line can start smoothly. Use this checklist with your machine supplier and local electrician before confirming dispatch.
1. Confirm the actual machine layout
Ask for the equipment footprint, working side, operator positions, maintenance access and required clearances for your selected configuration. Mark these on a scaled floor plan. Measure usable floor space after accounting for pillars, doors, stairs and existing equipment. A straight line may look simple on a drawing but leave too little room for roll changes or finished-board handling.
Include the infeed and outfeed space for every stage. A corrugation line may need room for paper rolls, board transfer, cutting, stacking, printing, slotting and finishing. If you are still choosing equipment, compare the sequence on the Tarun Enterprises machine range with the space available in your plant.
2. Check unloading and entry access
Record the gate opening, route from the unloading point, internal door sizes and turning space. Confirm how heavy assemblies will be lifted and moved. The installation team should know about overhead obstructions, floor level changes and loading restrictions before the vehicle reaches your site. Arrange suitable lifting support and a clear route in advance.
3. Plan electrical supply with a qualified professional
Request the electrical requirements for the exact machines ordered, including connected load, supply type, protection, earthing and cable routing. Have a qualified electrician assess the site supply and prepare the installation. Do not rely on a generic power number for a different model. Leave safe access to panels and emergency stops; do not run temporary cables across operator walkways.
4. Map material movement
Draw the route from kraft paper or sheet storage to infeed, through each process, then to finished-carton storage or dispatch. Keep movement paths clear enough for the handling method you actually use. Note where rejected sheets and trim will be collected. A factory can have enough square footage yet lose production time when rolls, pallets and operators cross the same narrow route.
5. Prepare the floor and utilities
Check that the floor is level and suitable for the supplied equipment and its handling method. Confirm foundation or anchoring requirements with the supplier for the specific line. Identify compressed air, glue preparation, ventilation or drainage needs only where the chosen machines require them. Prepare these connections before commissioning rather than making assumptions from another plant’s setup.
6. Set up commissioning and training
Agree who will receive the machines, inspect for transit damage and sign off the delivered items. Keep sample kraft paper, boards, glue and expected carton specifications ready for trial runs. Nominate operators and maintenance staff to attend training. Record trial settings, observed board quality, safety checks and any open actions before routine production starts.
Questions to send with your quotation request
- Available floor length and width, including pillars and access doors.
- Required board width, 3 ply or 5 ply output and target daily volume.
- Current machines that the new equipment must connect to.
- Site location, unloading method and planned installation date.
These details let the supplier discuss a realistic layout and installation scope. For the machine selection itself, read our corrugation machine selection guide.
Frequently asked questions
What should I measure before ordering?
Measure usable floor space, gate and door clearances, unloading access and the full material route. Share a marked floor plan rather than only the building’s outer dimensions.
Should electrical work be finished before delivery?
Plan it early using the exact equipment requirements. A qualified electrician should confirm readiness before the installation team arrives.
Can installation start while other machines remain in production?
That depends on the available separation, access and site safety plan. Agree a phased layout with the supplier before scheduling delivery.
What is needed for a useful trial run?
Provide representative materials and your target finished-board specifications. Ensure the operators who will run the line attend commissioning.
Request a site-specific quotation
Send your factory dimensions, intended machine list, working width, output target and location to Tarun Enterprises. Call +91 62807 60628 to discuss the installation plan and request a quotation.